Like most websites Modern Railways uses cookies. We use cookies to ensure that we give you the best experience on our website. If you continue without changing your settings, we'll assume that you are happy to receive all cookies on Modern Railways website. However, if you would like to, you can change your cookie settings at any time. Find out more

Continue

East Coast bank holiday works completed

Photo: Flat crossing replacement: new infrastructure is installed at Newark.

 

Major works on the East Coast main line over the August bank holiday weekend were successfully completed by Network Rail.

The lynchpin of the work was replacement of the flat crossing at Newark, where the ECML crosses the Nottingham to Lincoln line, with this work taking place across the three days of the bank holiday weekend. At the southern end of the route, re-control of signalling from King’s Cross Power Signal Box to York Rail Operating Centre (ROC) saw King’s Cross station closed completely for two days, while other work included overhead line improvements and progress with installation of a new bay platform at Stevenage for terminating trains from the Hertford loop. NR says further closures as part of the East Coast upgrade are planned from early 2020.

Elsewhere, the August bank holiday saw replacement of track on the West Coast main line between Bletchley and Leighton Buzzard and between Adlington and Cheadle Hulme in Greater Manchester. In Anglia overhead line structure replacement continued on the Southend Victoria line, along with work connected with the London Overground extension to Barking Riverside and the installation of new track between Camden Road and Willesden Junction on the North London line.

Posted in News

NEVER MISS AN ISSUE...

Our Instant Issue Service sends you an email whenever a new issue of Modern Railways is out. SAVE ON QUEUES - FREE P&P